Research Workplan
July 1, 2013 send
out email to TAC members to solicit research topics
August 1-8, 2013 convene
all the TACs/POCs
August 12, 2013 compile
outcomes of TACs and POCs meetings/various research topics by TAC
August 22, 2013 make
available list of research topics for review at the Chairs meeting
establish evaluation criteria for determining the viability of research
subject matter
September 2013 working
with the proponents of potential research projects, staff compiles research
projects using the Commission approved research evaluation criteria.
October 2013 Chair
meeting to consider and recommend list of research topics for consideration by
the Commission
Oct. /Nov. 2013 solicit qualified entity to do the
research
Dec.2013/Jan.2014
draft contract for research and implementation
Jan./Feb.2014 start
contract (contract time frame 1 – 3 years)
Funding is contingent upon budget appropriation and must be spend
within the Fiscal year.
June 15, 2014 complete
research or partial research