Florida Building Commission
August 22, 2014
Legal Report
Tradewinds
Island Grand
5500 Gulf Boulevard
St. Pete Beach,
Florida
PLUMBING TAC
DS2014-066 by Edward Rojas
of the City of Doral As modified by TAC
Question: When
classifying an Assembly use as a Business according to the 2010 Florida
Building Code, Building, Chapter 3, section 303.1 exception 1. Does the
2010 Florida Building Code, Plumbing, chapter 4, section 403.2, Separate
Facilities, Exception 3 also apply?
Answer: Yes. The project in question (i.e. business
occupancy with floor area of 1,711 Square feet and occupant load of less than 50 persons)
would fall within the scope of Section 403.2, Exception 3 of the 2010 Florida
Building Code, Plumbing.
ELECTRICAL TAC, ENERGY TAC
DS-2014-075 by Sprague
Owings of Marion County As modified by TAC
Question 1: Does the use of a
mini-split or other equipment that is listed as an A/C unit or heat pump that
has a dehumidification mode and a promised to only run in the dehumidication mode exempt the reclassification of a
Category I, II, or III sunroom to a IV or V?
Answer: The
answer is No. As per sections R301.2.1.1.2 of the 2010 Florida
Building Code, Residential, a mini split system that could provide cooling or
heating to the sunroom would place the room in category IV or V, depending on
thermal isolation or lack thereof from the primary structure. All
applicable code requirements would apply. To be exempt, the unit
must comply with Section 101.4.8.5(5) of the 2010 Florida Building Code, Energy
Conservation.
Question 2: Does a dehumidification mode and signed affidavit to only run the unit
in dehumification mode circumvent the listing &
labeling intent and circumvent all other application code requirement.
Answer: See answer to question #1.
FIRE TAC
DS 2014-083 by Eric Neilinger
of Fire Alarm Systems and Security Inc.
Question 1: Does a UL listed
integrated Fire alarm and smoke control system meet the intent of 909.12?
Answer: Answer is not
possible. The Commission has no authority to determine whether a
listed system meets the intent of the Code. In fact, determination of whether a
listed product meets code is subject to the design of the engineer of record
and the review and approval by the local authority having
jurisdiction.
Question: 2) Do we have
to separate the one integrated system into two separate control panels?
Answer: Yes, as per 909.16 of
the FBC, Building, separate control panels are required. However, as
per section 909.16.2 of the FBC, Building, an integrated system is permitted as
designed by the engineer of record and approved by the local authority having
jurisdiction.
Question 3) As a minimum code
compliant system does 909 require the Fire Fighter smoke control panel to be a
separate graphic display panel?
Answer: Answer is not
possible; the term “graphic display” is not utilized in Section 909.16.
Determination of whether a product meets code is subject to the design of the
engineer of record and review and approval from the local building authority
having jurisdiction.
Question 4) To meet minimum code
compliance will the installation of a UL listed integrated Fire Alarm and Smoke
Control system that meets all the elements of 909.16 meet the intent of 909 for
a Fire Fighter smoke control panel?
Answer: No, as per 909.16 of
the FBC, Building, and separate control panels are required. However, as per section 909.16.2 of the FBC,
Building, an integrated system is permitted as designed by the engineer of
record and approved by the local authority having jurisdiction.
Note: The TAC voted to
approve staff analysis & also supported a motion to dismiss the DEC
Statement based on comments made by Petitioner during the meeting.
PLUMBING TAC
DS 2014-084 by Gary Kozan of Ridgeway Plumbing Inc.
Question: The
issue is
whether a water heater
that is installed in a garage, but at the same elevation as the interior
finished floor, is required to have a pan.
Answer: No. As per Chapter 2, Definition of “Habitable Space”. A garage
is not habitable space and no pan is required even if the heater is installed
at the same elevation as the finished floor of the structure.
STRUCTURAL TAC, PRODUCT APPROVAL POC
DS2014-086 by
Joe Hetzel of DASMA
Question 1: If a vent is installed in the door, is the
state approval still valid if the approval does not include allowance for a
vent?
Answer: No, installation of the vent in the
door in question is considered modification to the said approval. The state
approval would not be valid because the product was approved based on specific
testing and evaluation/limitation of use which did not include the allowance
for a vent. However, modifications to the product in question can be
made per F.S. 553.8425 (3), if such modifications are acceptable to the
building official and substantiated through sufficient evidence submitted to
the local building official to demonstrate compliance with the code or the
intent of the code, including such evidence as certifications from a Florida
registered architect or Florida professional engineer.
Question 2: Is there any difference in the answer to #1
above for a door involving a vent for flood control versus a vent for air
ventilation?
Answer: No. Also, see answer to question #1
Question 3: Does the size of the vent itself make a
difference in the answer to Question #1?
Answer: No. Also, see answer to question #1.
CODE
ADMINISTRATION TAC
DS2013-089 petitioned by T.A.
Krebs, Architect, T.A. Krebs, LLC.
Question: Is the applicant for a single
family residence remodeling/addition, not undergoing a change of occupancy,
complying with FBC-Residential required to demonstrate compliance with an
FBC-Existing Building compliance method selected by the Building Official?
Answer: With the understanding that as per Section 101.5 of the Florida Building
Code (FBC), Existing Building, selection of the appropriate method of
compliance for the project in question is subject to the discretion of the
applicant and not the building official; the answer to the question is “No”. As
per Sections 302.1 and 303.1 of the 2010 Florida Building Code, Existing
Building, compliance of the project in question with the 2010 FBC-Residential
is an acceptable alternative for demonstrating compliance with the 2010 FBC, Existing
Building.