Florida Building Commission 2012 Workplan
Annual Administrative Tasks
2013
Florida Building Commission Annual Report (Workplan
Priority: 3) |
||||||||||||||||||||
Task |
Schedule |
|||||||||||||||||||
Commission identifies and receives Summary of Issues Recommendations Report |
2/6/13 |
|||||||||||||||||||
Commission adopts Report and Recommendations to 2013 Legislature |
4/10/13 |
|||||||||||||||||||
Editorial review (DBPR) |
4/11/13-5/13
|
|||||||||||||||||||
Chairman’s final approval |
6/12/13 |
|||||||||||||||||||
Commission’s 2013 Report delivered |
6/30/13 |
|||||||||||||||||||
Status
Pending: % Complete |
||||||||||||||||||||
0% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Origination:
Commission. Annual task authorized by statute. |
||||||||||||||||||||
Florida Statutes Tasks
Screen
Enclosures Workgroup |
||||||||||||||||||||
Task |
Schedule |
|||||||||||||||||||
Develop rule for implementing an alternative design method for screen enclosures allowing for removal of screen section to accommodate high-wind events consistent with the provisions of the Florida Building Code. |
2012 - 2013 |
|||||||||||||||||||
Appoint Screen
Enclosures Workgroup |
April 3, 2012 |
|||||||||||||||||||
Workgroup Meetings Final signoff and review delivered at RDW |
April 3, 2012 May 2012 July-August
|
|||||||||||||||||||
Rule
Development Workshop (Concurrent with FBC meeting) |
August 7, 2012 |
|||||||||||||||||||
Approve
Statement of Estimated Regulatory Costs |
October
9, 2012 |
|||||||||||||||||||
Rule
Adoption Hearing (if requested by teleconference) |
November
2012 |
|||||||||||||||||||
Rule Effective date |
January 2, 2013 |
|||||||||||||||||||
Status
Pending: % Complete |
||||||||||||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
90% |
|
|
|
Origination:
2012 Florida Legislation SB704ER |
||||||||||||||||||||
2013 FBC Code Update Development Tasks
2013
Update to the Florida Building Code—Combine Primary Update and Glitch
Revisions in a Single Rule Proceeding (Workplan
Priority: 2) |
|||||||||||||||||||
Task |
Schedule |
||||||||||||||||||
Primary
Code Development Phase: |
|
||||||||||||||||||
2011 NEC published and available to the public; |
01/2011 |
||||||||||||||||||
2012 International Codes published and available to the public; |
09/2011 |
||||||||||||||||||
Commission selects 2012 I Codes and 2011 NEC as foundation for 2013 FBC (Note:
The 6 month delay between I Codes available to public and Commission
selection as base for the next Florida
Building Code edition was removed from law in 2010) |
12/6/2011 |
||||||||||||||||||
Staff evaluates Florida amendments resulting from direction of the Legislature and Commission initiatives to propose for inclusion in the 2013 FBC |
1/2012 – 6/2012 |
||||||||||||||||||
Period
for public to propose modifications to the 2012 I Codes |
7/1/2012 – 8/1/2012 |
||||||||||||||||||
TACs consider proposed modifications |
10/4-17 |
||||||||||||||||||
Commission considers TAC recommendations Rule Workshop |
2/4-5/2013 |
||||||||||||||||||
Draft 2013 (Florida Supplement plus I Codes) posted online |
3/1/2013 |
||||||||||||||||||
Glitch
Correction Phase: |
|
||||||||||||||||||
Period to propose glitch modifications to draft 2013 FBC |
3/1/2013 – 5/1/2013 |
||||||||||||||||||
TACs consider proposed glitch modifications and develop public comment |
6/10-11/2013 |
||||||||||||||||||
Commission considers proposed glitch mods
and TAC comments |
6/12/2013 |
||||||||||||||||||
Final
Draft 2013 FBC posted online |
7/12/2013 |
||||||||||||||||||
Final Rule Hearing on 2013 FBC/Commission
approves final version of Code |
8/13/2013 |
||||||||||||||||||
Rule
Submitted to Secretary of State and Supplement posted online |
9/2013 |
||||||||||||||||||
2013 FBC effective date |
3/2014 |
||||||||||||||||||
|
|||||||||||||||||||
Sub-Tasks |
|||||||||||||||||||
a.
Amend BCIS Forms and Commission Rule for Code Modification Proposals |
|||||||||||||||||||
Authorize initiation of rule amendment |
12/6/11 |
||||||||||||||||||
Rule development workshop |
1/31/12 |
||||||||||||||||||
|
|||||||||||||||||||
b.
Review 2012 I Codes and 2012 NFPA 1 and NFPA 101 for Conflicts |
|
||||||||||||||||||
Joint Fire TAC/Fire Code Advisory
Council review and recommendations |
5/29/2012 |
||||||||||||||||||
Glitch
proposals considered during “Glitch
Correction Phase” |
|
||||||||||||||||||
|
|
||||||||||||||||||
|
|||||||||||||||||||
2016 FBC and Cycles Going Forward |
|||||||||||||||||||
2015 I Codes published and available |
9/2014 |
||||||||||||||||||
Draft Code development period |
4/2015 – 6/2015 |
||||||||||||||||||
Glitch amendments period |
6/2015 – 8/2015 |
||||||||||||||||||
2016 Code Adopted (rule filed with Secretary of State) |
9/2015 |
||||||||||||||||||
2015 Code effective date |
3/2016 |
||||||||||||||||||
|
|
||||||||||||||||||
Status
Pending: % Complete |
|||||||||||||||||||
|
|
|
|
|
30% |
|
|
|
|
|
|
|
|
|
|
|
|
|
100% |
Origination:
Statutory Requirement to update the FBC every 3 years. |
|||||||||||||||||||
Note: Dates
indicated in red are scheduled Commission meetings.
Commission Initiated Tasks
Building Code System Uniform Implementation Evaluation
Workgroup |
||||||||||||||||||||
Task |
Schedule |
|||||||||||||||||||
Evaluate how well the Commission's efforts to create a unified building code have been implemented throughout the State |
2012 – 2013 |
|||||||||||||||||||
Chair recommends and Commission votes to
convene Workgroup |
January 31, 2012 |
|||||||||||||||||||
Appoint Building Code System Uniform Implementation
Evaluation Workgroup |
October
9 |
|||||||||||||||||||
Workgroup Meetings |
October, 2012 December, 2012 |
|||||||||||||||||||
Workgroup
submits status report to Commission |
December 4, 2012 |
|||||||||||||||||||
Consensus
projects conducted for recommendation specifics |
TBD |
|||||||||||||||||||
Status
Pending: % Complete |
||||||||||||||||||||
5% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Origination:
Commission. Chairman’s recommendation. |
||||||||||||||||||||
Glitch
Amendments to the 2010 Florida Building Code (Workplan Priority: 9) |
||||||||||||||||||||
Task |
Schedule |
|||||||||||||||||||
Address glitch issues as identified by section 553.73(8), Florida Statutes, identified within the 2010 Florida Building Code |
5/2012-9/2012 |
|||||||||||||||||||
Commission authorizes Rule Development Workshop to consider proposed amendments to the 2010 Florida Building Code meeting criteria of 553.73( ), F.S. |
5/04/2012 |
|||||||||||||||||||
TAC review of issues identified as
“glitches” for comment at the Rule Development Workshop |
5/14/2012 – 6/05/2012 |
|||||||||||||||||||
Rule Development Workshop before the
Commission |
6/12/2012 |
|||||||||||||||||||
Supplemental Rule Development Workshop
before the Commission |
8/07/2012 |
|||||||||||||||||||
Approval of Statement of Estimated
Regulatory Costs Analysis |
10/9/2012 |
|||||||||||||||||||
Rule Adoption Hearing (if requested by
conference call) |
11/12 |
|||||||||||||||||||
Rule filed with Department of State |
12/28
|
|||||||||||||||||||
Status
Pending: % Complete |
||||||||||||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
75% |
|
|
|
|
|
|
Origination:
Commission. |
||||||||||||||||||||
Wind
Standards for Asphalt Shingles (Workplan
Priority: 8) |
||||||||||||||||||||
Task |
Schedule |
|||||||||||||||||||
Review research on shingle performance and determine if building code requirements are adequate and propose any necessary modifications. |
2011 - 2012 |
|||||||||||||||||||
Appoint an Asphalt Shingle Work Group |
10-11-11 |
|||||||||||||||||||
UF/US DOE/Commission research project |
2009 – 10/2011 |
|||||||||||||||||||
Work Group meetings |
12/7/11 3/2012 |
|||||||||||||||||||
Propose modifications for 2013 FBC (if
warranted) |
4/2012 |
|||||||||||||||||||
Review results of UF research for future
code modifications |
2012-2013 |
|||||||||||||||||||
|
|
|||||||||||||||||||
Status
Pending: % Complete |
||||||||||||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
100% |
|
Origination:
Commission. Annual Task. |
||||||||||||||||||||
Threshold
Building Inspections for Structural Alterations of Existing Structures (Workplan Priority: 6) |
||||||||||||||||||||
Task |
Schedule |
|||||||||||||||||||
Determine how the special inspections of threshold buildings statute applies to structural alterations to threshold buildings |
2011 - 2012 |
|||||||||||||||||||
Appoint a Threshold Building Inspections
Work Group |
10-11-11 |
|||||||||||||||||||
Workgroup Meeting I |
12/5/2011 |
|||||||||||||||||||
Workgroup Meeting II (Pending FBPE’s
clarification and participation) |
TBD |
|||||||||||||||||||
Report to the Commission and Board of
Professional Engineers |
|
|||||||||||||||||||
Status
Pending: % Complete |
||||||||||||||||||||
|
10% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Origination:
Commission. Annual Task. |
||||||||||||||||||||
Evaluate
Hurricane Wind Pressure and Rain Criteria for Soffit Systems and establish
Labeling Requirements (Workplan
Priority: 6) |
||||||||||||||||||||
Task |
Schedule |
|||||||||||||||||||
Phase I: Appoint Workgroup |
03/19/08 |
|||||||||||||||||||
Include task in UF components and cladding
contract |
03/08 |
|||||||||||||||||||
Workgroup meetings |
11/06/08 02/04/09 04/08/09 07/09 – 09/09 |
|||||||||||||||||||
Recommendations ready to propose for 2010
FBC |
02/10 |
|||||||||||||||||||
Report to Structural TAC and Commission |
02/10/10 |
|||||||||||||||||||
Proposals for
2010 FBC submitted for adoption |
03/10 |
|||||||||||||||||||
|
||||||||||||||||||||
Phase II: Workgroup and
research for phase II, development of product evaluation standards initiated |
|
|||||||||||||||||||
Review research
recommendations and develop proposed 2013 FBC mods |
03/12 |
|||||||||||||||||||
Submit 2013 FBC
modification proposals by |
06/12 |
|||||||||||||||||||
Status
Pending: % Complete Phase
I |
||||||||||||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
100% |
|
Status
Pending: % Complete Phase II |
||||||||||||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
100% |
|
Origination:
Commission. Stakeholder request. |
||||||||||||||||||||
Hurricane
Performance Standards for Hinged Entry Doors (Workplan Priority: 9) |
||||||||||||||||||||
Task |
Schedule |
|||||||||||||||||||
Evaluate current FBC standards for hurricane related performance of hinged entry doors and recommend changes deemed critical to performance |
2011 - 2012 |
|||||||||||||||||||
Appoint a Hinged Door Wind Performance Work
Group |
12/6/2011 |
|||||||||||||||||||
Workgroup meetings |
5/23/12 |
|||||||||||||||||||
Report to the Commission |
6/11/12 |
|||||||||||||||||||
Status
Pending: % Complete |
||||||||||||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
100% |
|
Origination:
Commission. Annual Task. |
||||||||||||||||||||
Determination
of Equivalency of the 2010 FBC, Energy- Commercial Buildings to US Department
of Energy Designated Standard - and Certification to DOE |
||||||||||||||||||||
Task |
Schedule |
|||||||||||||||||||
Staff evaluation |
1/2012 - 5/2012 |
|||||||||||||||||||
Report to the Energy TAC |
5/24/2012 |
|||||||||||||||||||
Report to Commission for approval of certification
letter to US DOE |
6/11/2012 |
|||||||||||||||||||
Status
Pending: % Complete |
||||||||||||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
100% |
|
Origination:
Commission. Annual Task. |
||||||||||||||||||||
Amend
Rules to Establish Fees (Workplan
Priority: 5) |
||||||||||||||||||||
Task |
Schedule |
|||||||||||||||||||
· Accessibility Code Waivers · Declaratory Statements · Non-Binding Opinions |
||||||||||||||||||||
Conduct workshop to discuss which programs
to charge fees |
10/13/10 |
|||||||||||||||||||
Further action on rule adoption suspended pursuant to
Governor Scott’s Executive Order. |
01/11 |
|||||||||||||||||||
Conduct rule
development workshop |
TBD |
|||||||||||||||||||
Conduct Rule Adoption Hearing |
TBD |
|||||||||||||||||||
File with
the Department of State (if no notice of change) |
TBD |
|||||||||||||||||||
Effective
date |
TBD |
|||||||||||||||||||
Status
Pending: % Complete |
||||||||||||||||||||
|
|
|
20% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Origination:
Legislative assignment. |
||||||||||||||||||||
Workplan Tasks Resulting from 2010 Legislation: HB 7243
Develop
Recommendations that Increase Recycling and Composting and the Use of
Recyclable Construction Materials and Construction and Demolition Debris (Workplan Priority: 10) |
||||||||||||||||||||
Task |
Schedule |
|||||||||||||||||||
Review
provisions of the International Green Building Code to determine if it, as a
voluntary standard, encourages recycling, composting and the use of
recyclable construction materials and construction and demolition debris |
2012 |
|||||||||||||||||||
Recommendations to Commission for inclusion
in 2013 annual report. |
2/6/13
|
|||||||||||||||||||
|
|
|||||||||||||||||||
Status
Pending: % Complete |
||||||||||||||||||||
0% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Origination:
Legislative assignment. |
||||||||||||||||||||
Commission Workplan Prioritization
Exercise Results 2012
Workplan
Prioritization Exercise Results 2011 February
1, 2011 |
||
Workplan
Topics (Task/Topic #) |
Average (5
to 1) |
Overall
Ranking |
1. 2010 Update to FBC (5.) |
4.53 |
1 |
2. Glitch amendments to 2010 FBC (6.) |
4.37 |
2 |
3. Report to 2012 Legislature (1.) |
4.32 |
3 |
4. Integration of Accessibility Law
(DOJ SAD) into FBC (8.) |
4.11 |
4 |
5. Code amendments directed by
Legislature (18.) |
4.11 |
4 |
6. Amend rules to establish fees:
waivers/declaratory statements/opinions (20.) |
3.84 |
6 |
7. Triennial BCS Assessment (21.) |
3.84 |
6 |
8. Bedroom definition for septic tank
sizing (DOH) (9.) |
3.58 |
8 |
9. Corrosive gypsum board (DOH) (10.) |
3.16 |
9 |
10. Recommendations: increase recycling
and composting, and recyclable construction materials (22.) |
2.79 |
10 |
Workplan
Prioritization Exercise Results 2012 January
31, 2012 |
||
Workplan
Topics (Task/Topic #) |
Average (5
to 1) |
Overall
Ranking |
11.) Certification of Florida
Accessibility Code (DOJ) |
4.53 |
1 |
12.) 2013 Update & Glitch to FBC |
4.47 |
2 |
1.) Report to 2013 Legislature |
4.40 |
3 |
7.) Triennial Florida Building Code
System Assessment (Phase III) |
4.20 |
4 |
18.) Amend rules to establish fees:
waivers/decs./opinions |
3.73 |
5 |
15.) Soffit criteria and labeling |
3.40 |
6 |
14.) Threshold inspections existing
buildings |
3.40 |
6 |
13.) Wind standards for asphalt shingles |
3.33 |
8 |
16.) Hinged entry door standards |
3.27 |
9 |
19.) Recommendations: increase recycling
and composting, and recyclable construction materials (directed by
Legislature) |
2.80 |
10 |