DEC REQUEST DS-2014-097 STAFF ANALYSIS
ISSUE: DS-2014-097. Petitioner David G. Karins, seeks a
Declaratory Statement on section 3109.1.1 Exception of the Florida Building Code, Building.
Petitioner seeks
clarification of the following questions:
Question 1: Does
[FBC-Building] 3109.1.1 apply to the work described in the above petition
information? The work is not substantial
improvement of or additions to existing habitable structures and was legally
designed and constructed prior to the establishment of the CCCL.
Question 2: Does 3109.1.1
Exception require (contrary to the regulatory scheme within the
jurisdiction of the DEP) that the subject existing buildings constructed before
the establishment of the CCCL requirements be brought into conformance with FBC
3109.4 Construction Standards, if repair work is
performed at above-grade foundation components comprised of replacing hurricane
straps, repairing cracks, repairing spalls or densifying concrete or masonry,
assuming such repair work has no measurable interference with the coastal
system and such work does not constitute "rebuilding" and is less
than "substantial"?
Background:
Situation:
This petition
concerns a project on Longboat Key that is seaward of the Coastal Construction
Control Line, was constructed at various times between 1950 and 1974 and is
non-compliant as to current flood elevation requirements. The project includes repairs
to buildings of the earlier vintage that are constructed on reinforced masonry
piers. These piers are weathered, in some cases cracked and their connections
to the wood framing above are in various stages of deterioration including
fully compromised. The buildings of the later vintage (early 1970's) that are
constructed on spread footings under reinforced concrete columns/piers below
the first living level. The reinforced concrete columns/piers are spalled and
cracked due to corrosion of the reinforcing steel but are readily repairable in
accordance with International Concrete Repair Institute guidelines and the
American Concrete Institute Repair Code (ACI 562). All of the required repairs
are readily achievable without any appreciable impact on the existing coastal
system. The
project does not constitute substantial improvements or substantial repair and
does not involve correcting substantial structural damage.
The Petitioner
states in his Dec. submittal that FDEP has made it clear that repair/additions to foundations are permissible within
the regulatory scheme without triggering construction standards requirements
even though they do not fall within the exemption in 161.053(11)(a), which is
the source document for FBC 3109.1.1 Exception.
He further stated that DEP has issued exemptions for repairs to concrete
piers/columns below the first living level as well as for repairs to columns
directly supported by footings below grade at beachfront properties. Karins Engineering Group, Inc. Similar projects on which such exemptions
have been issued include Gulf Place Condominium on Holmes Beach, FL,
Fisherman’s Gove Condominium on Siesta Key, FL, and Dunes Chalet Condominium on
Boca Grande, FL.
2010 Florida Building
Code, Building
Section 3109.1.1.
The provisions of Section 3109 shall ensure that structures
located seaward of the coastal construction control line are designed to resist
the predicted forces associated with a 100-year storm event and shall apply to
the following:
1. All
habitable structures which extend wholly or partially seaward of a coastal
construction control line (CCCL) or 50-foot (15.3 m) setback line.
2. Substantial
improvement of or additions to existing habitable structures.
3. Swimming
pools that are located in close proximity to a habitable structure or
armoring. An environmental permit from the Florida Department of Environmental
Protection, requiring special siting considerations to protect the beach-dune
system, proposed or existing structures and public beach access, is required
prior to the start of construction. The environmental permit may condition the
nature, timing and sequence of construction of permitted activities to provide
protection to nesting sea turtles and hatchlings and their habitat, including
review, submittal and approval of lighting plans.
Exception: The standards for buildings seaward of a CCCL
area do not apply to any modification, maintenance or repair of any
existing structure within the limits of the existing foundation which does not require, involve or
include any additions to, or repair or modification of, the
existing foundation of that structure.
(EMPHASIS ADDED)
3109.4 Construction standards.
3109.4.1 Pile foundations. All
habitable structures shall be elevated on, and securely anchored to, an
adequate pile foundation. Pile
foundations for habitable structures shall be designed to withstand all
reasonable anticipated erosion, scour and loads resulting from a 100-year storm
including wind, wave, hydrostatic and
hydrodynamic forces acting simultaneously with typical structural (live and
dead) loads. All habitable structures
should be anchored to their pile foundation in such a manner as to prevent
flotation, collapse or lateral displacement. The elevation of the soil surface
to be used in the calculation of pile reactions and bearing capacities for
habitable structures shall not be greater than that which would result from
erosion caused by a 100-year storm event.
Calculation of the design grade shall account for localized scour
resulting from the presence of structural
components. Design ratio or
pile spacing to pile diameter should not be less than 8:1 for individual piles
located above the design grade. Pile caps shall be set below the design grade
unless designed to resist increased flood loads associated with setting the cap
above the design grade, but at or below the natural grade. Pile penetration
shall take into consideration the anticipated loss of soil above the design
grade.
Exceptions:
c. The
armoring must have sufficient continuity or return walls to prevent flanking
under the design storm from impacting the proposed construction.
d. The armoring must withstand the static and
hydrodynamic forces of the design storm.
3109.4.2 Walls below the 100-year storm
elevation. No substantial walls or partitions shall be
constructed below the level of the first finished floor of habitable
structures. All other walls shall be designed to break away.
3109.2 Definition.
SUBSTANTIAL IMPROVEMENT.
See Section 1612.
REBUILDING. See
definition of “Substantial improvement.”
SUBSTANTIAL
IMPROVEMENT. Any repair, reconstruction,
rehabilitation, addition or improvement of a building or structure, the cost of
which equals or exceeds 50 percent of the market value of the structure
before the improvement or repair is started. If the structure has sustained
substantial damage, any repairs are considered substantial improvement
regardless of the actual repair work performed. The term does not, however,
include either:
1. Any project for improvement of a building
required to correct existing health, sanitary or safety code violations
identified by the building official and that are the minimum necessary to
assure safe living conditions.
202 Definitions:
Repair - The reconstruction or renewal of any part
of an existing building for the purpose of its maintenance. (Emphasis
added)
2010 Florida Building
Code, Existing Buildings Section 202 Definitions:
Repair - The patching, restoration and/or minor replacement of
materials, elements, components, equipment and/or fixtures for the purposes of
maintaining such materials, elements, components, equipment and/or fixtures in
good or sound condition.
ALTERATION. Any
construction or renovation to an existing structure other than a repair or
addition. Alterations are classified as Level 1, Level 2, and Level 3.
SECTION 403
ALTERATION—LEVEL 1
403.1 Scope.
Level 1 alterations
include the removal and replacement or the covering of existing
materials, elements, equipment,
or fixtures using new materials, elements, equipment, or fixtures that serve
the same purpose. Level 1 alterations shall not include any removal, replacement or covering of existing
materials, elements, equipment or fixtures undertaken for purpose of repair as defined in Chapter 2 and described in Section 402. [Emphasis Added]
[F] SECTION 1409
WATER SUPPLY FOR FIRE PROTECTION
1409.1 When required. An approved
water supply for fire protection, either temporary or permanent, shall be made
available as soon as combustible material arrives on the site.
DCA07-DEC-179 (Based
on the 2004 FBC)
- Whether the Petitioner is entitled to rely on the past consistent interpretations of the Florida Department of Environmental Protection (DEP), and its predecessor agency, the Florida Department of National Resources (DNR), regarding the application of the same regulatory language that is now set forth in section 3109 of the FBC (as evidenced by the past consistent history of permits issued) to determine what uses may occupy an enclosed space in the project that exists seaward of the CCCL and in between the FEMA/NFIP established base flood elevation and the lowest horizontal structural member as described in section 3109.3 of the FBC;
- Whether section 3109.3, Florida Building Code, Building (2004), applied in light of the historical application of language by the predecessor agencies permit use of enclosed space that exists seaward of the CCCL and in between base flood elevation and the lowest horizontal structural member to include retail shops, pool and other bars, snack bars, grills with portable cooking equipment, dining areas where the permanent kitchen is located landward of the CCCL or above the lowest horizontal structural member, toilet rooms and bathrooms, cabanas, recreational spaces such as gyms and card rooms and service/storage/back-of-house facilities.
- The Commission affirmatively answered both of the Petitioner’s inquires. The Petitioner is entitled to rely on the past consistent interpretations of the DEP and DNR to the extent that the historical application of the regulation is consistent with the current context of the FBC. The Petitioner has demonstrated that the contexts are consistent and that, under the particular circumstances of the proposed development, the regulations now contained in Section 3109.3 of the FBC, Building (2004) prohibit restaurants, residences and hotels; and permit use of enclosed space that exists seaward of the CCCL and in between base flood elevation and the lowest horizontal structural member to include retail shops, pool and other bars, snack bars, grills with portable cooking equipment, dining areas where the permanent kitchen is located landward of the CCCL or above the lowest horizontal structural member, toilet rooms and bathrooms, cabanas, recreational spaces such as gyms and card rooms and service/storage/back-of-house facilities, subject to appropriate permitting as required by law.
Staff Analysis: Based on the above facts and
circumstances, staff provides the following analysis:
Question 1: Does
[FBC-Building] 3109.1.1 apply to the work described in the above petition
information? The work is not substantial
improvement of or additions to existing habitable structures and was legally
designed and constructed prior to the establishment of the CCCL.
Answer/Option
1: Yes,
the proposed level of work constitutes a “repair” to the foundations of the
subject existing building which the exception (3109.1.1 Exception) does not
allow without conforming with the requirements of Section 3109.4 of the Florida
Building Code, Building.
Answer/Option
2: No,
historically, DEP/DNR had permitted several projects with similar circumstances
to that of the project in question without requiring conformance with the
elevation and design requirements of the “Coastal Construction Control Line”
provisions as depicted in Section 3109.4 of the 2010 Florida Building Code,
Building.
Question 2: Does 3109.1.1
Exception require (contrary to the regulatory scheme within the
jurisdiction of the DEP) that the subject existing buildings constructed before
the establishment of the CCCL requirements be brought into conformance with FBC
3109.4 Construction Standards, if repair work is
performed at above-grade foundation components comprised of replacing hurricane
straps, repairing cracks, repairing spalls or densifying concrete or masonry,
assuming such repair work has no measurable interference with the coastal
system and such work does not constitute "rebuilding" and is less
than "substantial"?
Answer/Option 1: Yes,
the proposed level of work constitutes a “repair” to the foundations of the
subject existing buildings and therefore, compliance with Section 3109.4 of the
Florida Building Code, Building would be required.
Answer/Option
2: No,
historically, DEP/DNR had permitted several projects with similar circumstances
to that of the project in question without requiring conformance with the
elevation and design requirements of the “Coastal Construction Control Line”
provisions as depicted in Section 3109.4 of the 2010 Florida Building Code,
Building.