ISSUE: DS 2013-092. Petitioner seeks a Declaratory Statement on an interpretation of Section 101.4.7 of the 2010 Florida Building Code, Energy Conservation.
Petitioner
in DS 2013-092 seeks clarification of the following questions:
Question 1: In
Section 101.4.7.1.2, does HB 269 overturn the code requirements for heat load
calculations?
Question 2: In
Section 101.4.7.1.2, Is the Design Star heat load calculation program an
approved method, for existing residential change outs? And is it approved for
all brands of a/c units (presently used for Rheem and Carrier)? If it is an
approved method, is its acceptance to be statewide (all building departments)?
Can a local building department not allow it if ruled accepted?
Question 3: Does HB
269 overturn the code requirements for duct sealing as stated in 101.4.6.1.1?
Is the duct sealing certification/form still required for existing residential
change outs?
Background:
1. In his petition,
Mr. Scott P. Greenberg, President of Temperature Systems, Inc,, requests clarification
of certain provisions of HB 269 concerning Section 101.4.7 of the 2010
Florida Building Code, Energy Conservation.
Mr. Greenberg is a
state-certified air conditioning contractor who is currently in the process of
performing a total residential air conditioner change out, replacing
existing equipment with new equipment. It is assumed that the existing duct
system will not be replaced.
2. HB 269 states, in part: “It is the intent of the Legislature that all
replacement air-conditioning systems in residential applications be installed
using energy-saving, quality installation procedures, including, but not
limited to, equipment sizing analysis and duct inspection. Notwithstanding
this section, existing heating and cooling equipment in residential
applications need not meet the minimum equipment efficiencies, including system
sizing and duct sealing.”
3. Section 101.4.7.1.2, Replacement equipment
sizing (mandatory), states: “An A/C contractor or licensed Florida PE shall
submit a nationally recognized method based sizing calculation to the code
official at the time of permit application for total replacement of the
condensing and evaporator components of HVAC systems in accordance with Florida
law and the provisions of Section 403.6.1 or Section 503.2.1, as applicable.”
4. Section 101.4.7.1.1, Duct sealing upon
equipment replacement (mandatory), states: “At the time of the total
replacement of HVAC evaporators and condensing units, all accessible (a minimum
of 30 inches (762 mm) clearance) joints and seams in the air distribution
system shall inspected and sealed where needed using reinforced mastic or code
approved equivalent and shall include a signed certification by the contractor
that is attached to the air handler unit stipulating that the work has been
accomplished. [with 3 exceptions].”
5. Section 101.4.7.1.3, Existing equipment
efficiencies, states: “Existing cooling and heating equipment need not meet the
minimum equipment efficiencies of Sections 403.6.2.2 or 403.6.2.3 except to
preserve the original approval or listing of the equipment.”
6. Section 403.6.1, Equipment sizing, reads:
“Heating and cooling equipment shall be sized in accordance with ACCA Manual S based
on the equipment loads calculated in accordance with Manual J or other approved
heating and cooling calculation methodologies, based on building loads for
the directional orientation of the building… The manufacturer and model number
of the outdoor and indoor units (if split system) shall be submitted along with
the sensible and total cooling capacities at the design conditions described in
Section 302.1. This Code does not allow designer safety factors, provisions for
future expansion or other factors which affect equipment sizing. System sizing
calculations shall not include loads created by local intermittent mechanical
ventilation such as standard kitchen and bathroom exhaust fans.”
7. Section 202, Definitions, defines the term
“Approved” as: “Approval by the code official as a result of investigation and
tests conducted by him or her, or by reason of accepted principles or tests by
nationally recognized organizations.”
Staff Recommendations: Based on the above facts and circumstances, staff provides the following recommendations in answer to proponent’s questions:
To Question 1, In Section 101.4.7.1.2, does HB
269 overturn the code requirements for heat load calculations [for total equipment replacement]?, the answer is YES, HB 269
preempts system sizing for replacement of existing equipment.
To Question
2, In Section 101.4.7.1.2, Is the Design Star heat load calculation program
an approved method, for existing residential change outs? the answer is that the code does
not approve specific calculation methods; approval is by the code official.
And is it approved for all brands of a/c units
(presently used for Rheem and Carrier)? the answer is that approval is by the code official.
If it is an approved method, is its acceptance to be
statewide (all building departments)? the answer is that it’s acceptance is not statewide, but is reserved to
the code official of the Authority Having Jurisdiction.
Can a local building department not allow it if
ruled accepted? the
answer is YES, the code official has the authority to not accept a given sizing
calculation program.
To Question
3, Does HB 269 overturn the code requirements for duct sealing as stated in
101.4.6.1.1? the
answer is YES, if the duct system itself is not replaced, HB 269 overturns the
code requirements for duct sealing as stated in Section 101.4.6.1.1.
To the
question Is the duct sealing certification/form still required for existing
residential change outs?, the
answer is YES, if the duct system itself is not replaced, HB 269 overturns the
code requirements for duct sealing as stated in Section 101.4.6.1.1.