HURRICANE RESEARCH ADVISORY
COMMITTEE RECOMMENDATIONS FOR CODE CHANGES TRACKING CHART
5/2/07
Recommendation |
Actions |
Targeted Code Change |
Action PlanandAssignment |
|
|
|
|
A bond break be provided between primary drainage planes and stucco renderings in drained assemblies. In simple terms this will require two layers of building paper or a layer of building paper over a plastic housewrap. |
HRAC recommended Expedited Amendment Commission approved Expedited |
Expedited Amendments 11/1/05 |
Completed |
The specification, rating and testing of WRB’s be consistent with their installed exposure – i.e. tested and rated as part of a stucco assembly. Appropriate performance specifications need to be developed for WRB’s used with stucco renderings and the Florida Building Code altered to require them. |
HRAC recommended Expedited Amendment Commission approved Expedited |
Expedited Amendments 11/1/05 |
Completed |
The Florida Building Code be altered to come into compliance with the International Residential Code to explicitly allow for the construction of unvented roof assemblies. |
HRAC recommended Expedited Amendment Commission approved Expedited |
Expedited Amendments 11/1/05 |
Completed |
Require application of exterior
surface coatings to |
HRAC recommended Expedited Amendment Commission approved Expedited |
Expedited Amendments 11/1/05 |
Completed |
Require wood, metal or other
structural support “ridge board” for tile attachment methods 1, 2 and 4A |
HRAC recommended Expedited Amendment Commission approved Expedited |
Expedited Amendments 11/1/05 |
Completed |
|
|
|
|
Recommendation |
Actions |
Targeted Code Change |
Action PlanandAssignment |
Require FBC approved pre-bagged mortar to attach hip and ridge tiles attachment methods 3 and 4B (pre-bagged mortar requirement applies to systems where mortar is the attachment component not systems utilizing ridge board and mechanical or adhesive-set) |
HRAC recommended Expedited Amendment Commission approved Expedited |
Expedited Amendments 11/1/05 |
Completed |
Require testing of ridge attachment systems according to SSTD 11 to establish wind up-lift resistance. |
HRAC recommended Expedited Amendment Commission approved Expedited |
Expedited Amendments 11/1/05 |
Completed |
Utilize an additional tile factor of 2-1 above that specified in SSTD 11 or TAS 101 to determine the “allowable overturning moment” or “attachment resistance expressed as a moment (Mf)” |
HRAC recommended Expedited Amendment Commission approved Expedited |
Expedited Amendments 11/1/05 |
Completed |
Prohibit component substitution without proper laboratory testing and FBC Product Approval |
HRAC recommended Expedited Amendment Commission approved Expedited |
Expedited Amendments 11/1/05 |
Completed |
Allow hip and ridge attachment systems with demonstrated performance equal ofr superior to that required by the identified systems |
HRAC recommended Expedited Amendment Commission approved Expedited |
Expedited Amendments 11/1/05 |
Completed |
Address requirements for installation instructions via Product Approval Workgroup Recommendations |
HRAC recommended Expedited Amendment Commission approved Expedited |
Expedited Amendments 11/1/05 |
Completed |
|
|
|
|
Recommendation |
Actions |
Targeted Code Change |
Action PlanandAssignment |
The moisture storage capacity of mass walls be increased by providing a “seat” at the base of these assemblies. |
HRAC recommended expedited amendment Commission rejected |
None |
Referred back to FHBA (recommendation was from FHBA water intrusion report) |
Define the terms “weather resistant” and “weather protection” |
HRAC recommended expedited amendment Commission rejected |
None |
Referred back to Central Florida BOAF Chapter to pursue its recommendation |
Delete the criteria of chapter 14 that deems walls constructed according to the masonry chapter and concrete chapter requirements to be weather resistant. |
HRAC recommended expedited amendment Commission rejected |
None |
Referred back to Central Florida BOAF Chapter to pursue its recommendation |
|
|
|
|
Require compliance with ANSI/SPRI
ES-1 for edge flashings and copings. |
HRAC recommended expedited amendment Commission deferred to glitch amendments |
Glitch Amendments 12/23/06 |
Completed |
Require compliance with ASTM
E-1592 for testing the uplift resistance of metal panel roof systems. (Note:
Require ASTM E-1592 for structural metal panel roof systems and UL 580 for
non-structural metal panel roof systems) |
HRAC recommended expedited amendment Commission deferred to glitch amendments |
Glitch Amendments 12/23/06 |
Completed |
Require asphalt shingles to
comply with UL 2390 testing and rating based on wind speed categories |
HRAC recommended expedited amendment Commission deferred to glitch amendments |
Glitch Amendments 12/23/06 |
Completed |
|
|
|
|
Recommendation |
Actions |
Targeted Code Change |
Action PlanandAssignment |
Require removal of existing
roof covering down to the deck and replacement of deteriorated sheathing in
areas where basic wind speed is 110 mph or greater. If existing sheathing
attachment does not comply with loads derived from Chapter 16, require
installation of additional fasteners to meet the loads. |
HRAC recommended expedited amendment Commission deferred to glitch amendments |
Glitch Amendments 12/23/06 |
Completed |
Make the requirements of 2001
FBC Section 1522 (Rooftop Mounted Equipment) applicable throughout the state
for all wind speeds. Include in Mechanical Volume also. |
HRAC recommended expedited amendment Commission deferred to glitch amendments |
Glitch Amendments 12/23/06 |
Completed |
|
|
|
|
Add criteria regarding wind and wind driven rain resistance of ridge vents. Attachment criteria require development but TAS 100A could be referenced for rain resistance. |
HRAC recommended adoption in post “expedited” amndment |
Deferred to further research |
|
Criteria for wind resistance of soffits should be developed and added. |
HRAC recommended adoption in post “expedited” amndment |
Residential- Glitch Amendments12/23/06; Building- 2007 FBC |
Residential- Completed Building- pending 2007 FBC Further research also |
Criteria for wind-driven rain resistance of soffits should be developed and added. |
HRAC recommended adoption in post “expedited” amndment |
Long range – post 2007 FBC update. |
Conduct R&D to establish criteria. Budget authority requested for 2007-08 |
Water managed window and door
installation requirements be developed and the Florida Building Code altered
to require them. |
HRAC recommended
adoption in post “expedited” amndment |
2007 FBC Update 10/1/08 |
Prescriptive default criteria developed by 3 national window groups and submitted for 2007 FBC Update |
|
|
|
|
|
|
|
|
Recommendation |
Actions |
Targeted Code Change |
Action PlanandAssignment |
Windows and doors be correctly rated and tested according to ANSI/AAMA 101. Mulled window units, double windows or composite windows be tested and held to the same requirements as single units. |
HRAC recommended
adoption in post “expedited” amndment |
Glitch |
Completed |
Water managed window and door installation requirements be developed and the Florida Building Code altered to require them. |
HRAC recommended
adoption in post “expedited” amndment |
2007 FBC Update 10/1/08 |
Prescriptive default criteria developed by 3 national window groups and submitted for 2007 FBC Update |
Water managed details for dryer vents, electrical panel boxes, electrical boxes, vent fan hoods be developed and the Florida Building Code Altered to require them. |
HRAC recommended
adoption in post “expedited” amndment |
Long range – post 2007 FBC update. |
Conduct R&D to establish criteria. FY 07-08 project. |
Remove the partially enclosed design option at the next code cycle. |
HRAC recommended
adoption in post “expedited” amndment |
Special FBC amendment 1/1/07 |
Automatically enacted by adoption of 2006 IRC as required by 2005 SB 442. Implemented early-Jan 2007 via HB 1-A |
Adopt ASCE 24-05 for elevation
requirements and flood resistant materials, equipment. |
HRAC recommended
adoption in post “expedited” amndment |
Out of Commission’s jurisdiction |
FEMA and Florida DCA coordination. Enacted by adoption of 2006 IBC and IRC. |
Re-evaluate the hazard
identification/mapping approaches in Coastal A/V Zones. |
HRAC recommended
adoption in post “expedited” amndment |
Out of Commission’s jurisdiction |
FEMA and Florida DCA coordination. Prepare and submit amendment. |
For hurricane shelters and EHPA, adopt wind speed recommended by Florida DCA in the State Emergency Shelter Program and the ASCE 7-02/2001 FBC wind speed map design wind speed plus 40 mph using Performance Criteria 3. |
HRAC recommended
adoption in post “expedited” amndment |
Out of Commission’s jurisdiction |
Florida DCA, DOE and School Board Association negotiation. |
|
|
|
|
Recommendation |
Actions |
Targeted Code Change |
Action PlanandAssignment |
Pressure relieved/baffled soffit assemblies be developed for vented roof assemblies and the Florida Building Code altered to require them. |
HRAC recommended adoption in post “expedited” amndment |
Long range – post 2007 FBC update. |
Conduct R&D to evaluate soffit water intrusion control methods. FY 07-08 project |
It is unlikely that a practical paint specification can be developed in the short term to address micro-cracking stucco issues as the relationships among water vapor permeability, mil thickness and elasticity are not known. It is recommended that these relationships be explored and that until these relationships are understood the Florida Building Code not be altered to require “elastomeric paints” on stucco renderings. |
HRAC recommended
adoption in post “expedited” amndment |
Long range – post 2007 FBC update. |
Conduct R&D on water penetration, absorption and transport through concrete and masonry wall assemblies to establish criteria for coatings or other water control measures. FY 07-08 project. |
Add technically-based criteria
regarding blow-off resistance of aggregate on built-up and sprayed polyurethane
foam roofs (Roof Coverings for Roofs with Slopes Less than 2:12). |
HRAC recommended
adoption in post “expedited” amndment |
Long range supported by R&D |
Conduct R&D to establish criteria. FY 07-08 project. |
Develop window water leakage test
and performance criteria specific to hurricane prone regions. |
HRAC recommended
adoption in post “expedited” amndment |
Long range supported by R&D |
Conduct R&D in support of AAMA standard development. FY 07-08.Windows Work Group |
Develop criteria that pertain to
attaching lightning protection systems. Include in the Electrical Volume
also. |
HRAC recommended
adoption in post “expedited” amndment |
Long range supported by R&D |
Support industry standard development activity. Tom Smith/FEMA |
|
|
|
|
Revise the |
HRAC recommended
adoption in post “expedited” amendment |
Legislature must change the law- Done Amend FBC by 7/1/07 |
Conduct Study as directed by 2005 Legislature |
Note: Red text indicates
recommendations for expedited amendments to FBC
Black
text indicates deferral to glitch amendment proceeding decided 6/28/05
Blue text indicates deferral to glitch amendment proceeding
decided 5/10/05
Purple text
indicates Commission deferral of HRAC recommended expedited amendments, to the
glitch amendment proceeding.