Review
and evaluation of the current Building Energy Rating System (BERS)
WORK
PLAN
Objective:       review
the current regulations, rules and business functions of the BERS and determine
whether improvement /changes to the program are needed.
Schedule:
Appoint Building Energy Rating System Steering
Committee                      6-7/ 2010
Conduct a survey to obtain feedback from users on
the BERS                     6-7/ 2010
            Send
out survey                                                                                  6
/29/2010
            Complete
survey                                                                                 7/22/2010
Steering Committee 1st meeting          (Gainesville)                                        10/2010
            Introduction
(DCA)
            Program
review - Presentations 
                        DCA
- Statutes and Rule
                        FSEC
– Program administration
                        National
program review
Steering Committee 2nd meeting         (TBD)                                       12/2010          
            Review
feedback from the survey (DCA)
            Identify
key topical issues for evaluation
            Rank/prioritize
key topical issues
            Formulate
recommendations for action
Steering Committee 3rd meeting (if
needed)                                                   2/2011